Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Aug 2023 110.56 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - bottom slab concrete work completed, side wall form work &column work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- 12 th lift concrete completed,slab shuttering on going & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam completed, column 3rd lift RCC completed. HTC(4305) completed. Palakkad Proj Dn AE 4
09 Aug 2023 110.56 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - bottom slab concrete work completed, side wall form work &column work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam completed, column 1 st lift RCC completed. HTC(4305) completed. Palakkad Proj Dn AE 4
08 Aug 2023 110.56 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - bottom slab concrete work completed, side wall form work &column work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam completed, column 1 st lift RCC completed. HTC(4305) completed. Palakkad Proj Dn AE 4
07 Aug 2023 110.56 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - bottom slab concrete work completed, side wall form work &column work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam completed, column 1 st lift RCC completed. HTC(4305) completed. Palakkad Proj Dn AE 4
05 Aug 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab concrete work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam concrete on going. HTC(4305) completed. Palakkad Proj Dn AE 4
04 Aug 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab concrete work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam shuttering on going. HTC(4305) completed. Palakkad Proj Dn AE 4
03 Aug 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab concrete work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - plinth beam shuttering on going. HTC(4305) completed. Palakkad Proj Dn AE 4
02 Aug 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab shuttering & steel work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - column concrete completed up to plinth level, earth filling on going. HTC(4298) completed. Palakkad Proj Dn AE 4
01 Aug 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab shuttering & steel work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - column concrete completed up to plinth level, earth filling on going. HTC(4298) completed. Palakkad Proj Dn AE 4
31 Jul 2023 110.17 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft 1st lift concrete completed , Wash water tank roof slab & trough concrete completed.Flash mixer- PCC completed. filter bed - structure completed & plastering workon going. OHSR -5th floor column concrete work completed, OHSR bottom slab shuttering & steel work progress. pipe galary PCC completed. Intake well (6 m dia)- 12 th lift concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR - column concrete completed up to plinth level, earth filling on going. HTC(4298) completed. Palakkad Proj Dn AE 4