Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
16 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed,column steel & box setting work above fourth brace beam on going. 10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed. |
Palakkad Proj Dn AE 4 |
|
13 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
12 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed. |
Palakkad Proj Dn AE 4 |
|
11 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed. |
Palakkad Proj Dn AE 4 |
|
10 Oct 2023 |
117.22 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed. |
Palakkad Proj Dn AE 4 |
|
10 Oct 2023 |
116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4412/5928 completed. |
Palakkad Proj Dn AE 4 |
|
09 Oct 2023 |
117.22 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. |
Palakkad Proj Dn AE 4 |
|
10 Oct 2023 |
177.22 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed, 1 st lift column concrete on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
09 Oct 2023 |
177.22 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed, 1 st lift column concrete on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed.
|
Palakkad Proj Dn AE 4 |
|