Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Oct 2023 116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. Palakkad Proj Dn AE 4
06 Oct 2023 116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. Palakkad Proj Dn AE 4
05 Oct 2023 116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. Palakkad Proj Dn AE 4
04 Oct 2023 116.48 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. Palakkad Proj Dn AE 4
03 Oct 2023 116.48 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. Palakkad Proj Dn AE 4
30 Sep 2023 116.46 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. Palakkad Proj Dn AE 4
29 Sep 2023 116.08 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. Palakkad Proj Dn AE 4
27 Sep 2023 116.08 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. Palakkad Proj Dn AE 4
26 Sep 2023 116.08 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam completed,column concrete on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4
25 Sep 2023 116.08 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam completed,column concrete on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4