Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Oct 2023 |
116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam concrete completed.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
06 Oct 2023 |
116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. |
Palakkad Proj Dn AE 4 |
|
05 Oct 2023 |
116.65 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab concrete completed. HTC -4360/5928 completed. |
Palakkad Proj Dn AE 4 |
|
04 Oct 2023 |
116.48 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
03 Oct 2023 |
116.48 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
30 Sep 2023 |
116.46 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
29 Sep 2023 |
116.08 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
27 Sep 2023 |
116.08 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia) cum pump house - column lintel level completed,approach bridge footing work progress. 5 LL OHSR -4th brace beam form work on going.10 LL OHSR: cover slab steel & shuttering work on going. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
26 Sep 2023 |
116.08 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam completed,column concrete on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
25 Sep 2023 |
116.08 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam completed,column concrete on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|