Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Sep 2023 113.08 km/169.845 km completed. WTP- structural work completed,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,pumphouse column steel work progress. 5 LL OHSR -second brace beam form work completed, column rising on going.10 LL OHSR: third lift of side wall completed.fourth lift shutering work progress .RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4
11 Sep 2023 113.08 km/169.845 km completed. WTP- structural work completed,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,pumphouse column steel work progress. 5 LL OHSR -second brace beam form work completed, column rising on going.10 LL OHSR: third lift of side wall completed.fourth lift shutering work progress .RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4
08 Sep 2023 113.08 km/169.845 km completed. WTP- structural work completed. . Intake well (6 m dia)-upto floor slab completed. 5 LL OHSR -second brace beam form work completed,10 LL OHSR: third lift of side wall completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4
07 Sep 2023 113.08 km/169.845 km completed. WTP- structural work completed. . Intake well (6 m dia)-upto floor slab completed. 5 LL OHSR -second brace beam form work completed,10 LL OHSR: third lift of side wall completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. Palakkad Proj Dn AE 4
05 Sep 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4
04 Sep 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4
02 Sep 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4
01 Sep 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4
26 Aug 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4
25 Aug 2023 113.08 km/169.845 km completed. Remaining HDPE, DI& PVC pipe laying in progress, PWD road work progressing, restoration work progressing & DLP for parali causeway starch 1 . WTP- ground floor & first floor brick masonry work ,lintel, ceiling plastering & sunshade progressing, clarifier -structural work completed & rotating bridge work (mechanical) on going. Clariflocculator plastering work completed & mechanical work on going. Chemical house- Alum , Lime tank side wall concrete work completed, Aerator - center shaft plinth beam concrete completed , Wash water tank roof slab & trough concrete completed. Flash mixer- foundation concrete completed. filter bed - structure completed & plastering work on going. OHSR - side wall third lift form work on going. pipe galley foundation slab RCC completed. Intake well (6 m dia)- roof slab concrete completed & leading channel chamber RCC work completed, Stair landing shuttering work on going.600 mm DI pipe fixed, Baby well - roof slab completed.5 LL OHSR -second brace beam form work on going, road restoration on going, HTC(4305) completed. Palakkad Proj Dn AE 4