Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Oct 2023 |
122.86 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4463/5928 completed. |
Palakkad Proj Dn AE 4 |
|
30 Oct 2023 |
117.85 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4450/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
28 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4450/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
27 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
26 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
25 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
21 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
20 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
19 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
18 Oct 2023 |
117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed.
|
Palakkad Proj Dn AE 4 |
|