Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Oct 2023 122.86 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4463/5928 completed. Palakkad Proj Dn AE 4
30 Oct 2023 117.85 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4450/5928 completed. Palakkad Proj Dn AE 4
28 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4450/5928 completed. Palakkad Proj Dn AE 4
27 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
26 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
25 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
21 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam shutering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
20 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
19 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4
18 Oct 2023 117.62 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift center shaft RCC completed & 5th lift shuttering on going. Intake well (6 m dia) cum pump house - column lintel level completed, approach bridge column shuttering progress. 5 LL OHSR -floor slab shuttering work progress. 10 LL OHSR: cover slab concrete completed. HTC -4432/5928 completed. Palakkad Proj Dn AE 4