Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jul 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -22%) | Kozhikode Project AEE 2 | |
29 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project AEE 2 | |
18 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project AEE 2 | |
14 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project AEE 2 | |
11 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project AEE 2 | |
03 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project AEE 2 | |
01 Jun 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -20%) | Kozhikode Project Dn EE | |
03 May 2021 | 88% completed ( Package 1-100%, Package 2-98%,Package 3-98% & Package 4 -10%) | Kozhikode Project AEE 2 | |
28 Apr 2021 | 88% completed ( Package 1-100%, Package 2-98%,Package 3-98% & Package 4 -10%) | Kozhikode Project AEE 2 | |
31 Mar 2021 | 87% completed ( Package 1-100%, Package 2-98%,Package 3-95% & Package 4 -10%) | Kozhikode Project AEE 2 |