Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Dec 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. .Package4-Stair case work and footing work in progress, Footing completed 55 out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . |
Kozhikode Project Dn AE5 |
|
24 Nov 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. .Package4-Today Stair case work and 4 footing started, Footing completed 49 out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . |
Kozhikode Project Dn AE5 |
|
10 Nov 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges.
.Package4-compound wall work in progress, site levelling work in progress. Footing of 49 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress |
Kozhikode Project Dn AE5 |
|
09 Nov 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-compound wall work in progress, site levelling work in progress. Footing of 49 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress |
Kozhikode Project Dn AE5 |
|
27 Oct 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-compound wall work in progress, site levelling work in progress. Footing of 42 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . |
Kozhikode Project Dn AE5 |
|
16 Oct 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 42 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress |
Kozhikode Project Dn AE5 |
|
12 Oct 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 42 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress |
Kozhikode Project Dn AE5 |
|
02 Oct 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 40 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress |
Kozhikode Project Dn AE5 |
|
25 Sep 2021 |
Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 39 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress |
Kozhikode Project Dn AE5 |
|
15 Sep 2021 |
Package 1 , 2 3 completed. package 4 -Footing of 38 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam & second brace beam work in progress. |
Kozhikode Project Dn AE5 |
|