Status Date Overall Project Status Project Officer Contact
03 Dec 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. .Package4-Stair case work and footing work in progress, Footing completed 55 out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . Kozhikode Project Dn AE5
24 Nov 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. .Package4-Today Stair case work and 4 footing started, Footing completed 49 out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . Kozhikode Project Dn AE5
10 Nov 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.236075955/- and Total Bill Paid Rs.218171975.final bill submitted.Package3- Work completed. Total expenditure Rs.126670608/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. .Package4-compound wall work in progress, site levelling work in progress. Footing of 49 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress Kozhikode Project Dn AE5
09 Nov 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-compound wall work in progress, site levelling work in progress. Footing of 49 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress Kozhikode Project Dn AE5
27 Oct 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-compound wall work in progress, site levelling work in progress. Footing of 42 completed out of 63 nos, Column work in progress , Plinth beam completed, First brace beam &second brace beam work in progress, column above second brace beam in progress . Kozhikode Project Dn AE5
16 Oct 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 42 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress Kozhikode Project Dn AE5
12 Oct 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 42 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress Kozhikode Project Dn AE5
02 Oct 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 40 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress Kozhikode Project Dn AE5
25 Sep 2021 Package1-Work completed. Total expenditure Rs.325013720/- final Bill paid to contractor on 24-06-2021 including Road restoration charges.Package2-work completed, Total Bill Submitted Rs.261066766/- and Total Bill Paid Rs.243157552.final bill submitted.Package3- Work completed. Total expenditure Rs.123303201/- final Bill paid to contractor on 29-08-2021 including Road restoration charges.Package4-Footing of 39 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam &second brace beam work in progress Kozhikode Project Dn AE5
15 Sep 2021 Package 1 , 2 3 completed. package 4 -Footing of 38 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam & second brace beam work in progress. Kozhikode Project Dn AE5