KIIFB-2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)
Project |
KIIFB-2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1) |
Project Code |
CLTKIIFB1117507 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB WSS to Koyilandy and adjoining Panchayath-Laying CWG main from Kayanna to Koyilandy Muncipality, Construction of 5 numbers of reservoirs to koyilandy Muncipality, Thurayoor G. P, Kottoor and Naduvannoor G.P |
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
850000000
|
AS Number |
GO (Rt) No.14/2017/WRD Dated 11/01/2017 |
TS Amount (Rs) |
826700000 |
TS Number |
KWA/CE/NR/31/2016-17,TS/2019-2020/2019/14951 |
Total Bill Submitted (Rs) |
700154837 |
Total Bill Paid (Rs) |
699894837 |
Population Benefitted |
185169 |
Capacity in MLD |
22.87 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
CWG main to Koyilandy Muncipality, Thurayoor G.P , Kottoor GP and naduvannoor G.P, construction of 3 reservoirs to koyilandy muncipality , one number to thurayoor GP and 27 LL capacity OHSR to Kottoor and Naduvannoor G.P |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package1 |
Kozhikode Project Dn |
|
2 |
KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package2 |
Kozhikode Project Dn |
|
3 |
KIIFB2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package3 |
Kozhikode Project Dn |
|
4 |
KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package4 |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Mar 2023 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.102926930/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1) All work completed. |
Kozhikode Project Dn AE5 |
|
13 Mar 2023 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.102926930/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 95% work completed, 4)Stair case work completed, 5)Watchman room work completed, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working completed, 9) Floor slab level hand rail work completed, 10)Pipe supplied, 11) 350mm and 400mm DI laying work completed, 12) Finishing work in progress.
|
Kozhikode Project Dn AE5 |
|
01 Mar 2023 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working progress, 9) Floor slab level hand rail work completed, 10)Pipe supplied, 11) 350mm and 400mm DI laying work in progress. |
Kozhikode Project Dn AE5 |
|
21 Feb 2023 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working progress, 9) Floor slab level hand rail work completed, 10)Pipe supplied, 11) 350mm and 400mm DI laying work in progress.
|
Kozhikode Project Dn AE5 |
|
10 Feb 2023 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4- 1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working progress, 9) Floor slab level hand rail work completed, 10)Pipe supplied. |
Kozhikode Project AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/09/2017 |
Scheduled date of Completion of the Project |
30 Jun 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
11 Jan 2017 |
TS Date |
19 Jan 2017 |