Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Mar 2021 | 87% completed ( Package 1-100%, Package 2-98%,Package 3-95% & Package 4 -10%) | Kozhikode Project AEE 2 | |
02 Mar 2021 | 86% completed ( Package 1-100%, Package 2-98%,Package 3-94% & Package 4 -10%) | Kozhikode Project AEE 2 | |
22 Feb 2021 | 85% completed ( Package 1-100%, Package 2-98%,Package 3-93% & Package 4 -10%) | Kozhikode Project AEE 2 | |
12 Feb 2021 | 84% completed ( Package 1-100%, Package 2-98%,Package 3-91% & Package 4 -10%) | Kozhikode Project AEE 2 | |
05 Feb 2021 | 83% completed ( Package 1-100%, Package 2-98%,Package 3-90% & Package 4 -10%) | Kozhikode Project AEE 2 | |
05 Feb 2021 | 83% completed | Kozhikode Project AEE 2 | |
27 Nov 2020 | 81% completed (Package1-100% completed, Package2- 95% completed, Package3- 88%completed, Package4-work started) | Kozhikode Project AEE 2 | |
27 Nov 2020 | 81% completed (Package1-100% completed, Package2- 94% completed, Package3- 87%completed, Package4-work started) | Kozhikode Project AEE 2 | |
11 Nov 2020 | 80% Completed | Kozhikode Project AEE 2 | |
10 Sep 2020 | 75%completed | Kozhikode Project AEE 2 |