Status Date |
Overall Project Status |
Project Officer |
Contact |
27 May 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Watchman room work in progress, 6)Hunch and side wall work in progress.
|
Kozhikode Project Dn AE5 |
|
20 May 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Watchman room work in progress, 6)Hunch and side wall work in progress.
|
Kozhikode Project Dn AE5 |
|
13 May 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All coloumns completed, 2)Floor slab part I RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Floor slab part II - RCC work completed, 6)Watchman room work in progress, 7)Hunch and side wall work started.
|
Kozhikode Project Dn AE5 |
|
10 May 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All coloumns completed, 2)Floor slab part I RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Floor slab part II - RCC work in progress, 6)Watchman room work in progress.
|
Kozhikode Project Dn AE5 |
|
30 Apr 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All coloumns completed, 2)Floor slab part I RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Floor slab part II Reinforcement work in progress, 6)Watchman room work in progress.
|
Kozhikode Project Dn AE5 |
|
19 Apr 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All coloumns completed, 2)Floor slab part I RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Floor slab part II shuttering work in progress, 6)Watchman room work in progress. |
Kozhikode Project Dn AE5 |
|
13 Apr 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All coloumns completed, 2)Floor slab part I RCC work completed, 3)Compound wall work in progress, 4)Stair case work in progress, 5)Floor slab part II shuttering work in progress, 6)Watchman room work in progress.
|
Kozhikode Project Dn AE5 |
|
05 Apr 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4- 1)Footing completed . 2) First brace beam completed .3)Plinth beam completed 4)second brace beam work completed,5)First brace colum completed,6) column above second brace beam in progress . 7)Compound wall work in progress.8)Stair case work in progress. 9)Floor slab RCC work in progress.10)watchman room work in progress.
|
Kozhikode Project Dn AE5 |
|
26 Mar 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4- 1)Footing completed . 2) First brace beam completed .3)Plinth beam completed 4)second brace beam work completed,5)First brace colum completed,6) column above second brace beam in progress . 7)Compound wall work in progress.8)Stair case work in progress. 9)Floor slab work in progress. |
Kozhikode Project Dn AE5 |
|
17 Mar 2022 |
Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4- 1)Footing completed . 2) First brace beam completed .3)Plinth beam completed 4)second brace beam work completed,5)First brace colum completed,6) column above second brace beam in progress . 7)Compound wall work in progress.8)Stair case work in progress. 9)Floor slab work in progress.
|
Kozhikode Project Dn AE5 |
|