Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 24 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
02 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 24 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
27 Jul 2021 | Package 1 , 2 3 completed. package 4 - footing of 24 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
22 Jul 2021 | Package 1 , 2 3 completed. package 4 - footing of 24 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
19 Jul 2021 | Package 1 , 2 3 completed. package 4 - footing of 12 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
15 Jul 2021 | Package 1 , 2 3 completed. package 4 - footing of 12 completed out of 63 nos, compound wall work in progress | Kozhikode Project AEE 2 | |
12 Jul 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -22%) | Kozhikode Project AEE 2 | |
09 Jul 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -22%) | Kozhikode Project AEE 2 | |
07 Jul 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -22%) | Kozhikode Project AEE 2 | |
05 Jul 2021 | 88% completed ( Package 1-100%, Package 2-100%,Package 3-100% & Package 4 -22%) | Kozhikode Project AEE 2 |