Status Date Overall Project Status Project Officer Contact
30 Aug 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam Reinforcement work 50% completed, 8) Roof slab - Concrete work 50% completed, 9) Column plastering working progress, 10) Floor slab level hand rail working in progress. Kozhikode Project Dn AE5
23 Aug 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam Reinforcement work 50% completed, 8) Roof slab - Concrete work 50% completed, 9) Column plastering working progress, 10) Floor slab level hand rail working in progress. Kozhikode Project Dn AE5
19 Aug 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam Reinforcement work in progress, 8) Column plastering working progress, 9) Floor slab level hand rail working in progress. Kozhikode Project Dn AE5
11 Aug 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam Reinforcement work in progress, 8) Column plastering working progress, 9) Floor slab level hand rail working in progress. Kozhikode Project Dn EE
01 Aug 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam shuttering work in progress, 8) Column plastering working progress, 9) Floor slab level hand rail working in progress. Kozhikode Project Dn AE5
22 Jul 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 3rd lift completed, 7) Roof slab and beam shuttering work in progress, 8) Column plastering working progress, 9) Floor slab level hand rail working in progress. Kozhikode Project Dn AE5
11 Jul 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4- 1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 2nd lift completed, 7) Roof slab shuttering and side wall work in progress. Kozhikode Project Dn AE5
09 Jul 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 2nd lift completed, work in progress. Kozhikode Project Dn AE5
28 Jun 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)side wall up to 2nd lift completed, work in progress. Kozhikode Project Dn AE5
14 Jun 2022 Package1- Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022 amount of Rs.260000/-. Package 2- Work completed. Total expenditure Rs.235994727/- final Bill paid to contractor on 18-12-2021 including Road restoration charges. Package 3- Work completed. Total expenditure Rs.101984382/- final Bill paid to contractor on 16-08-2021 including Road restoration charges. Package 4-1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 90% work completed, 4)Stair case work completed, 5)Watchman room work in progress, 6)Hunch and side wall work in progress. Kozhikode Project Dn AE5