06 Sep 2021 | Package 1 , 2 3 completed. package 4 - Footing of 34 completed out of 63 nos, Column work in progress, compound wall work in progress, Plinth beam completed, First brace beam in progress. | Kozhikode Project Dn AE5 | |
03 Sep 2021 | Package 1 , 2 3 completed. package 4 - footing of 34 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
26 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 33 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
25 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 30 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
23 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 30 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
18 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 28 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
16 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 28 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
11 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 28 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
09 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 28 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 | |
05 Aug 2021 | Package 1 , 2 3 completed. package 4 - footing of 28 completed out of 63 nos, compound wall work in progress | Kozhikode Project Dn AE5 |