Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Oct 2023 | 15000m laying completed, 1748connections completed, 15th and part bill submitted | Chavara AE | |
03 Oct 2023 | 15000m laying completed, 1740connections completed, 15th and part bill submitted | Chavara AE | |
27 Sep 2023 | 15000m laying completed, 1735 connections completed, 15th and part bill submitted | Chavara AE | |
23 Sep 2023 | 15000m laying completed, 1730 connections completed, 15th and part bill submitted | Chavara AE | |
20 Sep 2023 | 15000m laying completed, 1721 connections completed, 15th and part bill submitted | Chavara AE | |
16 Sep 2023 | 15000m laying completed, 1710 connections completed, 15th and part bill submitted | Chavara AE | |
12 Sep 2023 | 12000m laying completed, 1705 connections completed, 14th and part bill submitted | Chavara AE | |
08 Sep 2023 | 12000m laying completed, 1705 connections completed, 14th and part bill submitted | Chavara AE | |
05 Sep 2023 | 12000m laying completed, 1704 connections completed, 14th and part bill submitted | Chavara AE | |
26 Aug 2023 | 7000m laying completed, 1692 connections completed, 14th and part bill submitted | Chavara AE |