Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Mar 2023 | 4500 m laying completed, 1382 connections completed, 11th and part bill submitted | Chavara AE | |
18 Mar 2023 | 4500 m laying completed, 1382 connections completed, 11th and part bill submitted | Chavara AE | |
14 Mar 2023 | 4500 m laying completed, 1366 connections completed, 10th and part bill submitted | Chavara AE | |
10 Mar 2023 | 4500 m laying completed, 1366 connections completed, 10th and part bill submitted | Chavara AE | |
04 Mar 2023 | 4500 m laying completed, 1339 connections completed, 10th and part bill submitted | Chavara AE | |
02 Mar 2023 | 4500 m laying completed, 1333 connections completed, 10th and part bill submitted | Chavara AE | |
27 Feb 2023 | 4500 m laying completed, 1321 connections completed, 10th and part bill submitted | Chavara AE | |
24 Feb 2023 | 4500 m laying completed, 1311 connections completed, 10th and part bill submitted | Chavara AE | |
21 Feb 2023 | 4500 m laying completed, 1304 connections completed, 10th and part bill submitted | Chavara AE | |
17 Feb 2023 | 4500 m laying completed, 1304 connections completed, 10th and part bill submitted | Chavara AE |