Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Jul 2024 | 18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted | Chavara AE | |
02 Jul 2024 | 18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted | Chavara AE | |
29 Jun 2024 | 18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted | Chavara AE | |
27 Jun 2024 | 18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted | Chavara AEE | |
26 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE | |
23 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE | |
20 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE | |
17 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE | |
14 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE | |
11 Jun 2024 | 18950m laying completed, 2195 connections completed, 16 th and part bill submitted | Chavara AE |