Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Dec 2023 | 15000m laying completed, 1938connections completed, 15th and part bill submitted | Chavara AE | |
23 Dec 2023 | 15000m laying completed, 1913connections completed, 15th and part bill submitted | Chavara AE | |
19 Dec 2023 | 15000m laying completed, 1888connections completed, 15th and part bill submitted | Chavara AE | |
16 Dec 2023 | 15000m laying completed, 1863connections completed, 15th and part bill submitted | Chavara AE | |
12 Dec 2023 | 15000m laying completed, 1838 connections completed, 15th and part bill submitted | Chavara AE | |
08 Dec 2023 | 15000m laying completed, 1813 connections completed, 15th and part bill submitted | Chavara AE | |
05 Dec 2023 | 15000m laying completed, 1788connections completed, 15th and part bill submitted | Chavara AE | |
04 Dec 2023 | 15000m laying completed, 1783connections completed, 15th and part bill submitted | Chavara AE | |
29 Nov 2023 | 15000m laying completed, 1753connections completed, 15th and part bill submitted | Chavara AE | |
24 Nov 2023 | 15000m laying completed, 1753connections completed, 15th and part bill submitted | Chavara AE |