Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Feb 2024 | 15000m laying completed, 2029 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
30 Jan 2024 | 15000m laying completed, 2021 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
26 Jan 2024 | 15000m laying completed, 2021 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
18 Jan 2024 | 15000m laying completed, 2021 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
15 Jan 2024 | 15000m laying completed, 2021 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
12 Jan 2024 | 15000m laying completed, 2021 connections completed, 16 th and part bill submitted.work stopped due to delay in getting connection details from panchayath. | Chavara AE | |
09 Jan 2024 | 15000m laying completed, 1993 connections completed, 15th and part bill submitted | Chavara AE | |
04 Jan 2024 | 15000m laying completed, 1993 connections completed, 15th and part bill submitted | Chavara AE | |
01 Jan 2024 | 15000m laying completed, 1963 connections completed, 15th and part bill submitted | Chavara AE | |
29 Dec 2023 | 15000m laying completed, 1953connections completed, 15th and part bill submitted | Chavara AE |