Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Jul 2023 | 7000m laying completed, 1658 connections completed, 14th and part bill submitted | Chavara AE | |
04 Jul 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
30 Jun 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
27 Jun 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
23 Jun 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
20 Jun 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
20 Jun 2023 | 7000m laying completed, 1637 connections completed, 13th and part bill submitted | Chavara AE | |
16 Jun 2023 | 7000m laying completed, 1562 connections completed, 13th and part bill submitted | Chavara AE | |
13 Jun 2023 | 7000m laying completed, 1559 connections completed, 13th and part bill submitted | Chavara AE | |
09 Jun 2023 | 7000m laying completed, 1559 connections completed, 13th and part bill submitted | Chavara AE |