JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
Project |
JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Project Code |
KLMJJM092110690 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
74600000
|
AS Number |
489/2021/WRD |
TS Amount (Rs) |
68200000 |
TS Number |
13462/2021-2022 |
Total Bill Submitted (Rs) |
3988862 |
Total Bill Paid (Rs) |
3988862 |
Population Benefitted |
12000 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
09 Mar 2023 |
Coverage |
CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Chavara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jun 2024 |
18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted |
Chavara AE |
|
27 Jun 2024 |
18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted |
Chavara AEE |
|
26 Jun 2024 |
18950m laying completed, 2195 connections completed, 16 th and part bill submitted |
Chavara AE |
|
23 Jun 2024 |
18950m laying completed, 2195 connections completed, 16 th and part bill submitted |
Chavara AE |
|
20 Jun 2024 |
18950m laying completed, 2195 connections completed, 16 th and part bill submitted |
Chavara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/03/2022 |
Scheduled date of Completion of the Project |
09 Mar 2023 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
19 Nov 2021 |