Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 May 2023 | 7000m laying completed, 1519 connections completed, 12th and part bill submitted | Chavara AE | |
27 Apr 2023 | 7000m laying completed, 1515 connections completed, 12th and part bill submitted | Chavara AE | |
24 Apr 2023 | 7000m laying completed, 1515 connections completed, 12th and part bill submitted | Chavara AE | |
17 Apr 2023 | 4500 m laying completed, 1424 connections completed, 12th and part bill submitted | Chavara AEE | |
13 Apr 2023 | 4500 m laying completed, 1420 connections completed, 11th and part bill submitted | Chavara AE | |
10 Apr 2023 | 4500 m laying completed, 1412 connections completed, 11th and part bill submitted | Chavara AE | |
04 Apr 2023 | 4500 m laying completed, 1412 connections completed, 11th and part bill submitted | Chavara AE | |
31 Mar 2023 | 4500 m laying completed, 1408 connections completed, 11th and part bill submitted | Chavara AE | |
28 Mar 2023 | 4500 m laying completed, 1400 connections completed, 11th and part bill submitted | Chavara AE | |
24 Mar 2023 | 4500 m laying completed, 1395 connections completed, 11th and part bill submitted | Chavara AE |