Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2023 | 4500 m laying completed, 1300 connections completed, 10th and part bill submitted | Chavara AE | |
10 Feb 2023 | 4500 m laying completed, 1300 connections completed, 10th and part bill submitted | Chavara AE | |
10 Feb 2023 | 4500 m laying completed, 1300 connections completed, 9th and part bill submitted | Chavara AE | |
08 Feb 2023 | 4500 m laying completed, 1296 connections completed, 9th and part bill submitted | Chavara AE | |
06 Feb 2023 | 4500 m laying completed, 1292 connections completed, 9th and part bill submitted | Chavara AE | |
02 Feb 2023 | 4500 m laying completed, 1292 connections completed, 9th and part bill submitted | Chavara AE | |
30 Jan 2023 | 4500 m laying completed, 1280 connections completed, 9th and part bill submitted | Chavara AE | |
27 Jan 2023 | 4500 m laying completed, 1279 connections completed, 9th and part bill submitted | Chavara AE | |
24 Jan 2023 | 4500 m laying completed, 1279 connections completed, 9th and part bill submitted | Chavara AE | |
21 Jan 2023 | 4500 m laying completed, 1279 connections completed, 9th and part bill submitted | Chavara AE |