Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Mar 2023 Zone 4 A.792 HTCS and 35000m Laying completed. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 1820 HTCS completed 56632m Laying completed Kollam Project Dn AE
20 Mar 2023 Zone 4 A.792 HTCS and 35000m Laying completed. Zone 4 1003 HTCS completed 31287m Laying completed. Zone2.B 1820 HTCS completed 56632m Laying completed Kollam Project Dn AE
18 Mar 2023 Zone 4 A.792 HTCS and 35000m Laying completed. Zone 4 1003 HTCS completed 31287m Laying completed. Zone2.B 1820 HTCS completed 56632m Laying completed Kollam Project Dn AE
16 Mar 2023 Zone 4 A.792 HTCS and 35000m Laying completed. Zone 4 1003 HTCS completed 31287m Laying completed. Zone2.B 1820 HTCS completed 56632m Laying completed Kollam Project Dn AE
14 Mar 2023 Zone 4 A.Kadakkal-Chengamanadu PWD road ,pipe laying in progress.. Zone 4Ward no:21,Thennukonam to canal. Zone2.B 1820 HTCS completed 56632m Laying completed Kollam Project Dn AE
13 Mar 2023 Zone 4 A. House connection at ward 6 progress. Zone 4BHTC at Ward 18 Panavely, Laying work in progress at Karickom Thrikkanamangalam road. Zone2.B aying in ward 13 at kaduvapara In Anjanamkuzhy- Thalachira road, Kollam Project Dn AE
10 Mar 2023 Zone 4 A. NIRAPPIL-PANAVELY branch road ,pipe laying progress. Zone 4B 200mm DI pipe work in progress Zone2.Bchakkuvarakkal 140mm 8kg pipe laying Kollam Project Dn AE
07 Mar 2023 Zone 4 A. Kadakkal-Chengamanadu PWD road ,pipe laying in progress. Zone 4B HTCs work in progress at ward 21 Sadanandapuram Zone2.B laying in progress Kollam Project Dn AE
04 Mar 2023 Zone 4 A.(THALACHIRA-KURIYANI) branch road ,pipe laying in progress.* House connection at ward 8. Zone 4B 90mm,10kg/cm^2 PVC pipe laying work at ward no 20, Nirappuvila canals road. Zone2.B Node 39-35 140mm 8kg pipe laying in progress 140mm 8kg pipe laying ward 9 Chakkuvarakkal Kollam Project Dn AE
01 Mar 2023 Zone 4 A.Eettivila chirattakonam and palamukku Anganvaadi branch road 160mm 8kg 90 mm 8kg progressing Zone 4B140mm,6kg/cm^2 pvc pipe laying work at ward 18 Panavely. Zone2.BThalchira Ward 8 House connection work in progress,Trenching for 140mm 8 kg pipe laying at node 42 and Ward 9 chakkuvarakkal 160mm 8kg pipe laying Kollam Project Dn AE