24 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
22 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
20 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
18 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
17 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
13 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
11 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
10 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
08 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE
07 Apr 2023 Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. Kollam Project Dn AE