JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District

Project JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District
Project Code KLMJJM08206449
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION - Providing Functional Household Tap Connections, Distribution networks in Zone IIB , Zone IV A and Zone IV B,Laying 200mm DI Transmission main,Construction and Commissioning of 3LL GLSR at Eranoor,Compound Wall, Approach road and Maintenance of Existing tank at Vettikkavala Panchayaths in Kollam District
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 720000000
AS Number G.O(RI)No.541/202/WRD
TS Amount (Rs) 682100000
TS Number TS/2021-2022/2020/19977
Total Bill Submitted (Rs) 7691026
Total Bill Paid (Rs) 7691026
Population Benefitted 35455
Capacity in MLD 1.97
Actual Project Completion Date 24 Aug 2023
Coverage VETTIKAVALA PANACHAYATH
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM - Vettikavala Panchayath Part 1 Supplying and laying distribution network providing 3472 nos FHTCs in Zone II B Kollam Project Dn
2 JJM - Vettikavala Panchayath Part 3 Supplying and laying distribution network in zone IV A , providing 3000 No FHTCs , Construction of compound wall, construction of approach road, and maintenance of existing water tank at Kokkad Kollam Project Dn
3 JJM - Vettikavala Panchayath - Part II - Supplying and laying distribution network in Zone IV B, Providing 3000 nos FHTCs, Laying 200mm DI Transmission line, Construction and Commissioning of 3LL GLSR at Eranoor Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Dec 2023 Zone 4 A.2144 HTC installation and 77.19 km pipe laying work completed. DI distribution network progressing. Zone 4 B. 2080HTCS completed 79.19 km Laying completed. Zone2 B. 2760HTC installation & 80.88Km pipe laying(DI,PVC and GI) completed Kollam Project Dn AE
12 Dec 2023 Zone 4 A.2144 HTC installation and 77.19 km pipe laying work completed. DI distribution network progressing. Zone 4 B. 2080HTCS completed 79.19 km Laying completed. Zone2 B. 2760HTC installation & 80.88Km pipe laying(DI,PVC and GI) completed Kollam Project Dn AE
11 Dec 2023 Zone 4 A.2144 HTC installation and 77.19 km pipe laying work completed. DI distribution network progressing. Zone 4 B. 2080HTCS completed 79.19 km Laying completed. Zone2 B. 2760HTC installation & 80.88Km pipe laying(DI,PVC and GI) completed Kollam Project Dn AE
09 Dec 2023 Zone 4 A.2144 HTC installation and 77.19 km pipe laying work completed. DI distribution network progressing. Zone 4 B. 2080HTCS completed 79.19 km Laying completed. Zone2 B. 2760HTC installation & 80.88Km pipe laying(DI,PVC and GI) completed Kollam Project Dn AE
08 Dec 2023 Zone 4 A.2144 HTC installation and 77.19 km pipe laying work completed. DI distribution network progressing. Zone 4 B. 2080HTCS completed 79.19 km Laying completed. Zone2 B. 2760HTC installation & 80.88Km pipe laying(DI,PVC and GI) completed Kollam Project Dn AE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
04 Mar 2022 Pending Pending Road Cut Related Risk Sadanandapuram Vettikavala road No comments available. Pending

Duration & Sanction dates

Date of start of Project 01/05/2022
Scheduled date of Completion of the Project 24 Aug 2023
Expected date of Completion 24/08/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 17 Nov 2021

Other details

Project Officers View