Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied.Thalachira tank road ward:14 node 200-201 Laying Work progressing. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and 90mm 10kg pipe laying progressing at Narickal Jn . Zone 4. B.96 FHTCs completed 5039 m pipe laying completed. work progressing at ugarnmukku | Kollam Project HD | |
15 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied.Thalachira tank road ward:14 node 200-201 Laying Work progressing. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and 90mm 10kg pipe laying progressing . Zone 4. B.96 FHTCs completed 5039 m pipe laying completed. Panaveli ward 18 laying work progressing | Kollam Project Dn EE | |
14 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Thalachira tank road ward:14 node200-201 Laying Work progressing. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and Work in progress. Zone 4. B.96 FHTCs completed 5039 m pipe laying completed. 90mm 10kg pipe laying progressing | Kollam Project Dn EE | |
14 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Thalachira tank road ward:14 node200-201 Laying Work progressing. Zone 2B 1137 FHTCs Completed and 8754m pipe Laying completed and Work in progress. Zone 4. B 137 FHTCs Completed and 8754m pipe Laying completed and 90mm 10kg pipe laying progressing | Kollam Project Dn AE | |
13 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Thalachira Jn ward:8 node:53-540-542 Laying Work progressing. Zone 2B 137 FHTCs Completed and 8754 m pipe laying. 90mm 10kg pipe laying progressing. Zone 4. B 90mm 8kg Pipe laying work at ward no 19 Madathiyara Panavely | Kollam Project Dn AE | |
09 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Node 5-406, 90mm 6kg/cm^2 PVC laying in progress at ward 14. Aayiravalli temple - kokkadu . Zone 2B 137 FHTCs Completed and 8754 m pipe laying. Road restoration progressing on Canal road. Zone 4. B Work in progress work in progress at ward19 madathiyara panavely | Kollam Project Dn EE | |
08 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Node 61-610, 90mm 8kg/cm^2 PVC laying in progress at ward 8, Kallithala - Chakkuvarakkal road. 90mm 6 kg progressing at Kakkodo road. Zone 2B 137 FHTCs Completed and 8754 m pipe laying. Laying progressing at Chakkuvarakkal Zone 4. B Work in progress at ward 19 Madathiyara panavely. | Kollam Project HD | |
07 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Node: 4 - 400 - 402 Kokkadu-Paalur road, ward 14, 90mm 6kg cm^2 pipe laying in progress. Zone 2B 137 FHTCs Completed and 8754 m pipe laying completer,90mm 10kg Pipe Laying at Anjanamkuzhy. Zone 4. B Node 122-124- 90mm 6kg..patteri jn progressing. | Kollam Project HD | |
06 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Node:14-801-800 -8,90mm 6kg/cm^2 at ward 14 Kokkadu -Kurushumudu - Kokkadu, Node 700-702 Kokkodu-Chakkuvarakkal, and ward 16.Eettivila road pipe laying in progress 4. a Zone 2B 137 FHTCs Completed and 8754 m pipe Laying completed,90mm 10 kg pipe laying at Chakkuvarakkal ( ward 9). Zone 4. B Sadhanathapuram thrikkanamangalam road work progressing | Kollam Project Dn EE | |
05 Dec 2022 | Zone 4. A 65.15 PVC pipeline was supplied. Node 110-114, 90mm 6kg/cm^2 PVC laying in progress at ward 14. Zone 2B 137 FHTCs Completed and 8754 m pipe Laying completed, Node 15-150-152-153 90mm PVC 8 kg at Vattappara Jn progressing . Zone 4.B Pwd road panavely Patteri in road 122- 124 90mm 6kg | Kollam Project HD |