Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
12 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
10 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
08 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
05 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
02 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project HD | |
01 May 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
29 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
28 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
26 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE |