Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Dec 2022 Zone 4. A 65.15 PVC pipeline was supplied. Node: 46- 460, 90 mm 8 kg/cm^2 at ward 6 Chirattakonam - Pachur road in progress . Zone 4B - 380-381,90mm 8kg, ward 4, near Kannamkodukavu progressing , Zone 2B 137 FHTCs Completed and 8754 m pipe Laying completed, Ward 12 Kottavattom,Chakkuvarakkal work progressing Kollam Project Dn AE
01 Dec 2022 Zone 4. A 65.15 PVC pipeline was supplied. Node 420-417, 90mm 8kg/cm^2 PVC laying in progress at ward 6. Zone 4B -,Node -375-379,90mm 8kg(ward4 Kannamkodu ) progressing , Zone 2B 137 FHTCs Completed and 8754 m pipe Laying completed. Ward 12 Kottavattom node 7-17-173-170 progressing Kollam Project Dn AE
30 Nov 2022 Zone 4. A 65.15 PVC pipeline was supplied. 90mm 10kg/cm^2 PVC laying in progress at ward 7, Thalachira canal road. Node 524-528 ). Laying work in progress, Zone 4B -Ward 4, 383-384 progressing , Zone 2B 137 FHTCs Completed, and 8754 m pipe Laying completed and laying work in progress Kollam Project Dn AE
28 Nov 2022 Zone 4. A 65.15 PVC pipeline was supplied. Ward:15.kokkad road. Post Number: CMD/PC/12/25. NODE NUMBERcmd/ck/158/18/1.). Laying work in progress, Zone 4B -Ugramkunnu-panaveli laying work progressing, Zone 2B 137 FHTCs Completed, and 8754 m pipe Laying completed. laying work in progress Kollam Project Dn AE
25 Nov 2022 Zone 4. A 65.15 PVC pipeline was supplied. Ward:15.Pullipara road. Post Number: CMD/PC/12/25. NODE NUMBER:1-59. PVC PIPE (90mm 6kg). Laying work in progress, Zone 4B -Ugramkunnu laying work progressing, Zone 2B 137 FHTCs Completed, and 8754 m pipe Laying completed. Ward 13 Kokkad north 90mm 6 kg laying work in progress Kollam Project Dn EE
24 Nov 2022 Zone 4A 65.15 PVC pipeline supplied. Node 29-28, Eettivila junction to Altharamugal road 160mm 8kg/cm^2 PVC laying in progress, Zone 4B -Node 390-392,90mm8kg, ward 4, Kannamkodu work progressing, Zone 2B 137 FHTCs Completed and 8754 m pipe Laying completed. House connection -ward 10.Ward 9chakkuvarakkal,90mm pvc 6kg node -progressing Kollam Project Dn EE
23 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . House connection started Ward: 17 Ettivila - work in , Zone 4B -390-391 90mmpvc 10 kg, ward 4 work progressing, Zone 2B 274-279,90mm 8kg, ward 12, kottavattam pipelaying progressing Kollam Project Dn AE
21 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . Ward no:17, - Eettivila Jn Ambalatumvila road - laying work in progress, Zone 4B -160mm PVC Ernoor work progressing, Zone 2B Chakkuvarakkaol l90 mm 8kg pipelsying progressing Kollam Project HD
19 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . Ward no:17,Thalachira temple - Eettivila - laying work in progress, Zone 4B -Pipe layine at Ward 4 Kannamkodu, Ugramkunnu Road, Zone 2B Chakkuvarakkal Node 420-421. pipe laying Kollam Project Dn AE
18 Nov 2022 Zone 4A 65.15 PVC pipeline supplied . Ward no:17,Thalachira temple - Eettivila - laying work in progress, Zone 4B -Pipe layine at Ward 4 Kannamkodu Road, Zone 2B Ward9 pipe laying Kollam Project Dn AE