Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jan 2023 Zone 4 A.HTC Ward 17 Panaveli-Thattarakkodu road Zone 4B 90mm, 8kg/cm^2, PVC pipe laying at ward 21, Sadanadapuramone 2B House connection work Vettikavala ward 3 Kollam Project Dn EE
09 Jan 2023 Zone 4 A.FHTC Ward 17 progreessing. Zone 2B Work @PLAPPLLY progreessing Zone 4B90 mm, 8 kg/cm^2 PVC pipe laying work in progress at Ward 1, Uliyanadu Kollam Project Dn EE
07 Jan 2023 Zone 4 A. NNode:W17A2 ,75mm,8Kgcm^2 ,eettivila -altharamugal, branch road, ward 17, branch road pipe laying progress. Zone 2B Work @ ummannor Zone 4B 90 mm, 8 kg/cm^2 PVC pipe laying work in progress at Ward 1, Uliyanadu Kollam Project Dn EE
05 Jan 2023 Zone 4 A. NW17A2, 75mm 8kg/cm^2 PVC at Eettivila - Altharamugal branch road work. Progressing. Zone 2B 90mm 10kg pipe laying with T Joint connection at Chakkuvarakkal Zone 4B 90 mm, 8 kg/cm^2 PVC pipe laying work in progress at Ward 1, Uliyanadu Kollam Project Dn EE
03 Jan 2023 Zone 4 A. Node:-445-447-451-453,road ,90mm 10kg/cm^2,Chirattakonam -Palamukku branch road ,pipe laying in progress.Zone 2BWork progressing @ PLAPPLLY UMMANNOR ROAD Zone 4B 90mm 6kg Pipe laying work in progress at Nirappuvila Ward20 Kollam Project Dn EE
02 Jan 2023 Zone 4 A. House connection progressing at ward 14. Zone 2B Connection work progressing at ward 3. Zone 4B 90mm 6kg Pipe laying work in progress at Nirappuvila Ward20 Kollam Project Dn EE
01 Jan 2023 Zone 4 A *Node:-36-365,road ,90mm 10kg/cm^2, ward 17, nedungottmukkroad,pipe laying in progress.. Zone 2B Laying work progressing. Zone 4B 90mm 8kg Pipe laying work in progress at ward 1 Karikom Kollam Project Dn AE
23 Dec 2022 Zone 4. A 65.15 PVC pipeline was supplied. 90mm 10 kglaying progressing. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and pipe laying progressing at Narikkal. Zone 4. B.96 FHTCs completed 5039 m pipe laying completed 90mm 8kg Pipe laying work in progress at ward no 21 sadanandapuram Kollam Project Dn AE
20 Dec 2022 Zone 4. A 65.15 PVC pipeline was supplied. Node 689-690 kaduvapara,90mm laying progressing. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and pipe laying progressing at Chakkuvarakkal. Zone 4. B.96 FHTCs completed 5039 m pipe laying completed 90mm 8kg Pipe laying work in progress at ward no 21 sadanandapuram Kollam Project Dn AE
17 Dec 2022 Zone 4. A 65.15 PVC pipeline was supplied. Node 8-700, 90mm 10kg/cm^2 PVC laying in progress at ward 14. Zone 2B 137 FHTCs Completed and 8754m pipe Laying completed and 90mm 10kg pipe laying progressing at Narickal Jn. Zone 4. B.96 FHTCs completed 5039 m pipe laying completed 90mm 10kg Pipe laying work in progress at ward no 21 sadanandapuram Kollam Project HD