Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
03 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
01 Apr 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
31 Mar 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
30 Mar 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
29 Mar 2023 | Zone 4 A.951 HTC installation and 44406m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
27 Mar 2023 | Zone 4 A.951 HTC installation and 35000m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
24 Mar 2023 | Zone 4 A.951 HTC installation and 35000m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
23 Mar 2023 | Zone 4 A.951 HTC installation and 35000m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE | |
22 Mar 2023 | Zone 4 A.951 HTC installation and 35000m pipe laying work completed. DI distribution network progressing. Zone 4 B 1003 HTCS completed 31287m Laying completed. Zone2.B 2168 HTC installation & 56632m pipe laying completed. | Kollam Project Dn AE |