Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
12 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
10 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
08 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
07 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
05 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
03 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
01 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
31 May 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE | |
29 May 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn AE |