Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
26 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
24 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
23 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
22 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
21 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn EE | |
20 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
19 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
17 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE | |
15 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1344 HTCS completed 47 km Laying completed. Zone2.B 2372 HTC installation & 67Km pipe laying completed. | Kollam Project Dn EE |