Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
10 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
08 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
07 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
05 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
04 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
01 Jul 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
30 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
29 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE | |
28 Jun 2023 | Zone 4 A.1312 HTC installation and 57 km pipe laying work completed. DI distribution network progressing. Zone 4 B 1850 HTCS completed 64 km Laying completed. Zone2.B 2689 HTC installation & 73Km pipe laying completed. | Kollam Project Dn AE |