Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jan 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayat roads achieved, no provision for completing anchor block and road restoration. Phase II Package III - Revised and corrected electrical scheme drawings for submitting to Electrical Inspectorate Pathanamthitta and corrected drawing of the transformer room submitted. Adoor Project Dn AE 4
29 Jan 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayat roads achieved, no provision for completing anchor block and road restoration. Phase II Package III - Revised and corrected electrical scheme drawings for submitting to Electrical Inspectorate Pathanamthitta and corrected drawing of the transformer room was produced by the contractor and its submitted. Adoor Project Dn AE 4
29 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Revised and corrected electrical scheme drawings for submitting to Electrical Inspectorate Pathanamthitta and corrected drawing of the for transformer room was produced by the contractor and its submitted. Adoor Project Dn AE 4
25 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
24 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
22 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
21 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
20 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
18 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4
13 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III - Electrical drawings submitted to Electrical Inspectorate Pathanamthitta for approval. Transformer room drawing being corrected by contractor. Adoor Project Dn AE 4