Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2022 Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III work started. Adoor Project Dn AE 4
13 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
11 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
08 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
07 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
06 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
04 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
03 Jan 2022 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
30 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
28 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4