Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Jan 2022 | Phase II Package I Completed.In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing to completion . Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed .Phase II Package III work started. | Adoor Project Dn AE 4 | |
13 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
11 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
08 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
07 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
06 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
04 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
03 Jan 2022 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
30 Dec 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
28 Dec 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 |