Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Mar 2022 In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
14 Mar 2022 Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
14 Mar 2022 In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
11 Mar 2022 Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
11 Mar 2022 In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
10 Mar 2022 Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
10 Mar 2022 In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
09 Mar 2022 Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
09 Mar 2022 In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
08 Mar 2022 Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4