Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II

Project KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II
Project Code PTAKIIFB0117573
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This scheme comprises of Laying distribution system in Zone 1 to 11, Laying clear water pumping mains,Laying CWGM,Construction of pump house at Mundamala low level,Construction of GL tank at Mundamala top level ,Supply and erection of pump sets.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 414000000
AS Number GO(Rt)No.14/2017lWRD
TS Amount (Rs) 255200000
TS Number KWA/CE//SR/20/2016-17
Total Bill Submitted (Rs) 254313690
Total Bill Paid (Rs) 254313690
Population Benefitted 22121
Capacity in MLD 8.00
Actual Project Completion Date Date is not specified
Coverage Perunad and Athikkayam villages- Zone I,II,III,IV,V,VI and VII
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package I Adoor Project Dn
2 KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package II Adoor Project Dn
3 KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package III Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Aug 2022 Phase I & II completed, Phase III-Transformer room set out done Adoor Project Dn AE 4
10 Jun 2022 Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
03 Jun 2022 Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
31 May 2022 Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4
30 May 2022 Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval Adoor Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/10/2017
Scheduled date of Completion of the Project 31 May 2022
Expected date of Completion 30/04/2023

Processing Dates

AS Date 11 Jan 2017
TS Date 23 Jan 2017

Other details

Project Officers View