KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II
Project |
KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II |
Project Code |
PTAKIIFB0117573 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
This scheme comprises of Laying distribution system in Zone 1 to 11, Laying clear water pumping mains,Laying CWGM,Construction of pump house at Mundamala low level,Construction of GL tank at Mundamala top level ,Supply and erection of pump sets. |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Adoor Project Dn |
AS Amount (Rs) |
414000000
|
AS Number |
GO(Rt)No.14/2017lWRD |
TS Amount (Rs) |
255200000 |
TS Number |
KWA/CE//SR/20/2016-17 |
Total Bill Submitted (Rs) |
254313690 |
Total Bill Paid (Rs) |
254313690 |
Population Benefitted |
22121 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Perunad and Athikkayam villages- Zone I,II,III,IV,V,VI and VII |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package I |
Adoor Project Dn |
|
2 |
KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package II |
Adoor Project Dn |
|
3 |
KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package III |
Adoor Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Aug 2022 |
Phase I & II completed, Phase III-Transformer room set out done |
Adoor Project Dn AE 4 |
|
10 Jun 2022 |
Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval
|
Adoor Project Dn AE 4 |
|
03 Jun 2022 |
Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval |
Adoor Project Dn AE 4 |
|
31 May 2022 |
Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval |
Adoor Project Dn AE 4 |
|
30 May 2022 |
Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval |
Adoor Project Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/10/2017 |
Scheduled date of Completion of the Project |
31 May 2022 |
Expected date of Completion |
30/04/2023 |
Processing Dates
AS Date |
11 Jan 2017 |
TS Date |
23 Jan 2017 |