Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
20 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
17 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
16 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
14 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
10 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
09 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
06 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
02 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4
01 Dec 2021 Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started Adoor Project Dn AE 4