Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
22 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
20 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
17 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
15 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
13 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
11 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
10 Nov 2021 | Phase II package I completed,. In Phase II package II all works are in progress and completed 14230.00 m out of 13862 m CWPM& CWGM and 44860 m out of 45975 m distribution. pipe laying work is in progress. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL- plastering work in progress. Phase II package III work started | Adoor Project Dn AE 4 | |
09 Nov 2021 | Phase 2 Package I - Final bill settled. | Adoor Project Dn AE 4 | |
08 Nov 2021 | Phase 2 Package I - Final bill settled. | Adoor Project Dn AEE2 |