Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Feb 2022 Drawings submitted to Electrical Inspectorate for approval Adoor Project Dn AE 4
17 Feb 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
08 Feb 2022 Drawings submitted to Electrical Inspectorate for approval. Adoor Project Dn AE 4
07 Feb 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
04 Feb 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
03 Feb 2022 Phase II Package I completed. Package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road.. In Package III-Drawings submitted to Electrical Inspectorate for approval. Adoor Project Dn AE 4
03 Feb 2022 Remitted bank guarantee in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Adoor Project Dn AE 4
03 Feb 2022 Drawings submitted to Electrical Inspectorate for approval. Adoor Project Dn AE 4
01 Feb 2022 Phase II Package II - Remitted bank guarantee in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. Phase II Package III-Drawings submitted to Electrical Inspectorate for approval. Adoor Project Dn AE 4
01 Feb 2022 In Phase II package II all works are in progress and completed 13650 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayat roads achieved, no provision for completing anchor block and road restoration. Phase II Package III - Revised and corrected electrical scheme drawings for submitting to Electrical Inspectorate Pathanamthitta and corrected drawing of the transformer room submitted. Adoor Project Dn AE 4