Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Aug 2022 | Phase I & II completed, Phase III-Transformer room set out done | Adoor Project Dn AE 4 | |
10 Jun 2022 | Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
03 Jun 2022 | Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
31 May 2022 | Phase I& II completed, Phase III-Electrical schemes approved by the Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
30 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
28 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
26 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
25 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
24 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 | |
23 May 2022 | Phase I& II completed, Phase III-Electrical drawings submitted to Electrical Inspectorate and civil drawings submitted to WASCON for approval | Adoor Project Dn AE 4 |