Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
25 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
24 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
23 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
22 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
21 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
20 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. | Nattika Project Dn AE 2 | |
19 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- OHSR Tank site clearance work ongoing, Bench mark fixing and initial level marking at site completed and site clearance ongoing. | Nattika Project Dn AE 2 | |
18 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- OHSR Tank site clearance work ongoing, Bench mark fixing and initial level marking at site completed and site clearance ongoing. | Nattika Project Dn AE 2 | |
17 Jan 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- OHSR Tank site clearance work ongoing, Bench mark fixing and initial level marking at site completed and site clearance ongoing. | Nattika Project Dn AE 2 |