Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
05 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
04 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
03 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
02 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
01 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
31 Dec 2023 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
30 Dec 2023 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
29 Dec 2023 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2
28 Dec 2023 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at tank site completed. Nattika Project Dn AE 2