| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 14 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 13 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 12 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 11 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 08 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 07 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 07 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 06 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 05 Aug 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE |