Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Aug 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
02 Aug 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
01 Aug 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
31 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
30 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
29 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
28 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
26 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
25 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
23 Jul 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE