Status Date Overall Project Status Project Officer Contact
18 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
17 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
16 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
15 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
12 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
10 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
09 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -76 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
08 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
03 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
01 Sep 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE