Status Date Overall Project Status Project Officer Contact
11 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Chathannur PH Sn AE
10 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Chathannur PH Sn AE
09 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. Chathannur PH Sn AE
06 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 8 days. Chathannur PH Sn AE
05 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 8 days. Chathannur PH Sn AE
04 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 7 days. Chathannur PH Sn AE
03 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 6 days. Chathannur PH Sn AE
02 Jun 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 5 days. Chathannur PH Sn AE
31 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain. Chathannur PH Sn AE
30 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. 48 Chathannur PH Sn AE