| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 10 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 09 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 57 No.s. Geotagging of water connections -47 No.s. Interconnection 21 completed. | Chathannur PH Sn AE | |
| 06 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 8 days. | Chathannur PH Sn AE | |
| 05 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 8 days. | Chathannur PH Sn AE | |
| 04 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 7 days. | Chathannur PH Sn AE | |
| 03 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 6 days. | Chathannur PH Sn AE | |
| 02 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain for last 5 days. | Chathannur PH Sn AE | |
| 31 May 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and no work due to heavy rain. | Chathannur PH Sn AE | |
| 30 May 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. 48 | Chathannur PH Sn AE |