Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Dec 2025 90mm PVC pipe laying -2980m completed. 75mm PVC pipe laying -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -250 Nos. Interconnection 27 completed. Providing 250 FHTC's work completed. Chathannur PH Sn AE
31 Dec 2025 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
29 Dec 2025 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
26 Dec 2025 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
23 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
19 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
17 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
16 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
15 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
11 Dec 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE