| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2025 | 90mm PVC pipe laying -2980m completed. 75mm PVC pipe laying -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -250 Nos. Interconnection 27 completed. Providing 250 FHTC's work completed. | Chathannur PH Sn AE | |
| 31 Dec 2025 | 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 29 Dec 2025 | 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 26 Dec 2025 | 90mm PVC pipe laying work in progress -2980m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -230 No.s. Interconnection 27 completed. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 23 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 19 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 17 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 16 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 15 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 11 Dec 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -199 No.s. Interconnection 21 completed. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE |