Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
18 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
16 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
15 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
14 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
13 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
10 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
09 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
08 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE
07 Oct 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -94 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing Chathannur PH Sn AE