| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 18 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 16 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 15 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 14 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 13 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 10 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 09 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 08 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -114 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE | |
| 07 Oct 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -94 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing | Chathannur PH Sn AE |