| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 05 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 04 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 03 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 02 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 01 Jul 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 30 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 28 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 27 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE | |
| 26 Jun 2025 | 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing. Geotagging of water connections -62 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. | Chathannur PH Sn AE |